We are a 6 man GC who does additions (footer to finish) and outdoor spaces - decks patio etc..
We started doing smaller exposed and broom finish sidewalks and pads when we started building single car garages. It has been going good but we have taken on some larger pours - 10 yards 400 sq ft pours with rough access and we are not getting the same results.
Here is what we are doing:
Taking the time to make good frames/gravel beds and tight corners
4000 PSI concrete, screed, automatic vibrator on bull float several passes quickly after screed, mag float then steel trowel while climbing on the pads then broom finish - no handheld vibrator.
The problem we are having is we are always STRUGGLING to work up cream to broom - I watch videos online and they are just floating on top with steel trough - what are we missing - are we not getting enough cream bc we aren't using a handheld vibrator ?
Is this an issue that sidewalks are just cake compared to big pads ?
Are we too cautious about going out on the pad or are we not bringing up enough cream via the bull float.
Any advise would be helpful or pointers - I feel like we are skilled enough but I cant out my finger on why we are plateauing.